Monday, June 28, 2021

Sunday, June 27, 2021

6/27/2021



So, we have been a little laxed in posting this week, but today was pretty awesome! Finally got the rear wing complete and started the glass reinforcing. Things are really starting to look up here at the motor pool.

Tuesday, June 9, 2020

6/9/2020

Day two of the main flooring install. Still spending a lot of time waiting for primer to dry but, the floor is coming along nicely. We were about half way by the end of the day.

Monday, June 8, 2020

6/8/2020

So, today was the day to start the flooring. Boy did this not go as planned! 

The epoxy was very open after the sanding and it swallowed up the first coat of adhesive primer so, we put on a second coat on for good measure. Worked out very well in the end. The only down side was the dry time of better than 90 minutes per coat with the humidity being as high as it has been lately. Then there is the factor of Soldier A's short arms. He could only lay two foot sections at a time.  😂

Guess we will be doing flooring tomorrow as well.

Sunday, June 7, 2020

6/7/2020

Finally got the rest of the floor sanded as flat as it can be. Working on his hands and knees for the last few days has left soldier A walking around like a hunch back.  😂 But, it's now ready for the final flooring tomorrow.

Sunday, May 31, 2020

5/30/2020

Got the final road base layer down and compacted today which allowed the rebar to get started. There was also the regular yard maintenance to be done so, it was an awesome day overall.

Saturday, April 11, 2020

4/11/2020

Covid is still keeping us on lock down at the motor pool, but that just means getting more stuff done. today was lots more epoxy. 

Then Soldier A had to come to grips with the fact that no matter how much he hates to paint it was time to start sucking it up and put time in the bathroom prepping and priming the case work. All together a really good day.