Saturday, January 11, 2020

1/11/2020

This was a day of bouncing around. We have to take down another section of the existing structure so we can get the concrete truck close enough to the pour that we don't have to wheel barrow anything. Saves every bodies back!

In order to do the demo we our scaffolding set. Problem is they are worthless due to water damage, so they needed new decks. That was the first order of the day. Cut them out and started coating them with primer sealer, but the temps today were not working in our favor.

While waiting for the first 2 coats to dry we went into the storage container to find the ring for the bath light that holds the bulb. Naturally, we found it in the very last one. Once we had it we hauled butt over to the big orange store to get bulbs so we could fire up the bathroom.

Back at the motor pool as fast as we could, we turned the planks over and started the coating of the other sides. While the first coat was drying we installed the bulb ring and bulbs and fired up the bathroom. Another milestone!




No comments:

Post a Comment